Engineering Challenge
The project spanned three different site conditions — an RCC roof, a ballasted area and a vehicle parking zone — each requiring a distinct mounting method.


Uniworth
Low voltage termination at 400V distributed across multiple termination points.
P2 hot-dip galvanised raised structure on RCC roof; P1 anodised aluminium structure on ballast; L5 hot-dip galvanised solar carports.
The project spanned three different site conditions — an RCC roof, a ballasted area and a vehicle parking zone — each requiring a distinct mounting method.
NEEP engineered a P2 HDG raised structure for the RCC roof, a ballasted P1 aluminium structure for open roof areas, and HDG solar carports (L5) over the parking area, combining three structural solutions within a single project.


3 photos

Let our team take full responsibility from engineering and execution to commissioning, O&M readiness, and asset performance optimization.