NEEP Energy
1.6 MW Solar Project
Back to All Projects
Fast Cables

1.6 MW Solar Project

Fast Cables

PV Capacity
1.6 MW
Sector
Cable
Business Type
Industrial

Electrical Termination

Low voltage termination at 400V distributed across multiple termination points.

Mounting Structure

Anodised aluminium structure mounted on PEB shed roofing; L2 anodised aluminium structure mounted on ballast.

Engineering Challenge

Part of the available roof area could not accommodate drilled fixings, requiring a non-penetrative mounting method alongside a standard PEB roof solution.

Engineering Approach

NEEP combined an anodised aluminium PEB roof structure with a ballasted L2 aluminium system for the non-drill sections, avoiding roof penetration while maintaining structural stability.

Scope of Work

  • Complete project development including pre- sales activities
  • PV & Engineering Design facilitation
  • Supply & installation of anodized aluminum/ clamping assembly for PEB without drilling
  • Electrical installation, testing & commissioning

Partners

Partner
Partner

Project Gallery

3 photos

Solar EPC project background

Ready to Move from Design to Power-On?

Let our team take full responsibility from engineering and execution to commissioning, O&M readiness, and asset performance optimization.